12 July 2014

Timber flooring installation started...

We have been quite busy since we got the handover. Trying to get quotes and organise tradesmen in to do the remaining work around the house so we can move in asap.

Yesterday, we have carpet call delivered the timber flooring and we have our own tradesman - T.N Carpentry - on site to start the installation. We weren't there on site so we asked our tradesman to send a photo of the timber flooring to ensure it is the correct stock and it turns out to be the WRONG stock! The colour was completely different to the sample we received from the store though the same stock code UN0540 written on the box. We called Carpet Call immediately to check with their supplier and it turns out their supplier has packed the incorrect stock into box code UN0540 hence there was a colour discrepancy. O.M.G. So Carpet Call arranged the delivery man to exchange the stock immediately and this got sorted on the same day. Imagine we did not check with our tradesman and wrong stock got installed on the floor. Oh boy!

Today and tomorrow, T.N Carpentry continue on the timber flooring as carpet scheduled to be installed on Monday (by Carpet Call). Hopefully, they will have the correct carpet installed! Monday, we also have an electrician on site to install additional down lights and pendants around the house (due to complete within 3 days) and T.N Carpentry doing our driveway, concrete and landscaping (due to complete within a week hopefully). Will be a big day for all 3 tradesmen.

Schedule

Interior:

Paint feature walls - Pending
Install timber flooring to main area - Started. Due to complete by Monday
Install carpets to bedrooms and Media - Scheduled for Monday
Install additional lights points around the house - Scheduled for Monday-Wednesday
Install security screens/doors and blinds - Scheduled by Friday 25th July
Install blinds and curtains - Pending
Install kitchen appliances - oven, dishwasher, fridge, washing machine, dryer - Pending
Install Laundry and WIR cabinet - Pending for quote



Exterior:

Fix the damaged fence at back  - Pending
Driveway - Scheduled for Monday -Friday
Turf - front and back - Scheduled for Monday -Friday
Timber decking - porch and alfresco -  Scheduled for Monday -Friday
Concrete - back left side - Scheduled for Monday -Friday
Pebbles - back right side -  Scheduled for Monday -Friday
Retaining wall and garden bed at back -  Scheduled for Monday -Friday
Side gates -  Scheduled for Monday -Friday
Paint feature colour at porch piers - Pending


Just a few photos of timber flooring today. More photos to come with flooring, lights and outdoor landscaping.


A nice Saturday morning


Our lovely tradesman T.N Carpentry on the job

Timber flooring delivery (correct stock)

Entry nearly done

Hallway

Kitchen


Bedroom hallway to be done before carpet can be installed on Monday





Timber flooring for Living area





T.N Carpentry on the job






Incorrect timber flooring that got delivered. Got shocked when saw this. Thought that's how the timber we chose looks like.

Of course the correct timber flooring is on the left and the incorrect timber flooring is on the right. Same timber but different colour

03 July 2014

We got the keys!!

So the day we have been long waiting for has come. Looking back it has been an incredible journey from the initial thought of never going to build to a completed brand new home of our own design. Though there was frustration and long delay to finalise the contract at the beginning but the building stage itself was much smoother than our initial thought. Very glad we had a great site supervisor - Andy - who always on top of things, helped us, booked in all great trade men and did an incredible job.

At the handover, there was a trademan on site to install the last air vent at PDR and skylight at Media. The skylight could not be installed at centre of the room because there was a truss running across the middle so it has to be installed at one corner where our future down lights going to be installed. That definitely was not a preferred spot as it will ruin our lighting plan so we asked Andy if the skylight can be left on the roof uninstalled as later we will remove it anyway and without doubt Andy said to the tradesman not to install it. We were glad the skylight wasn't installed at it looks ugly and would cost us extra bucks to remove it.

So Andy went through with us every details of the house from how to take care of kitchen bench top to what we need to be aware when doing things near the termite mesh. So it was not like here is your key, congrats and goodbye. Couple of things was good to know and we could've done the wrong thing if was not told. There were still a few minor things which Andy will need to arrange the trade men back on site to finish off next week. Things such as interior/exterior paint touch up areas that was missed, small render chipped at the piers edge at front, replace the window aluminium corner frame at front that wasn't installed probably and install the missing laminate trim at microwave area.

  1. Install gas bottle - COMPLETED
  2. Andy to advise about the glass splashback - COMPLETED (Will receive a credit for incorrect splashback)
  3. Install exhaust fan at PDR - COMPLETED
  4. Install window corner frame at front - PENDING
  5. Install skylight at Media - N/A
  6. Install missing laminate piece at microwave - PENDING
  7. Paint touch up - PENDING

Things went smooth we handed over our final cheque and received the keys. Plantation Homes gave us a house warming gift and it was a coffee machine which we didn't expect. So now the keys are finally on our hands and it also means we going to start getting our own trade men in to finish off the interior and exterior jobs. Hoping to get these done within a month but fingers crossed.

Interior:

Paint feature walls
Install timber flooring to main area
Install carpets to bedrooms and Media
Install additional lighs points around the house
Install security screens/doors and blinds
Install kitchen appliances - oven, dishwasher, fridge, washing machine, dryer
Install Laundry and WIR cabinet



Exterior:

Fix the damaged fence at back
Driveway
Turf - front and back
Timber decking - porch and alfresco
Concrete - back left side
Pebbles - back right side
Retaining wall and garden bed at back
Side gates
Paint feature colour at porch piers


Photos coming shortly ..




01 July 2014

Final site inspection and counting down 2 days to go!

Our final site inspection was rescheduled to early this morning because there was a miscommunication with the meeting time yesterday and we had to head to work. When we got there at 7.30am today we saw the painters already started their touch up job. They have marked around the house with red and green spot stickers to mark the touch up area. To our amaze, they have marked a lot more than what we could identify though a couple spots was missed which Andy then marked the area for us.

The WIR light point has now moved to the correct position and toilet suite at Ensuite is also installed. With the discrepancy of the splash back colour Andy will meet with Colour Manager on site today to compare the two samples - one with old name one with new name - that she have and will advise us what is going to happen. Apparently, there was a name changed after our colour selection last year hence there was a colour difference. On the good side, Plantation Homes will be sending us a cheque to replace the damaged fence which we going to have it fixed in the coming weekends.

From the outside the temporary fence, bin and the ugly site toilet has been removed. Our weeds at the front also got removed and that going to save us time to remove it on the weekends.

Just a couple of things left tomorrow before the handover on Thursday. Getting very very close now and we are very excited :))

  1. Install gas bottle - PENDING
  2. Electrician to move the ceiling light point at WIR to centre - COMPLETED
  3. Andy to advise about the glass splashback - PENDING
  4. Andy to advise about the dent on the fence - COMPLETED
  5. Install the last toilet suite - COMPLETED
  6. Install exhaust fan at PDR - PENDING
  7. Install window corner frame at front - COMPLETED
  8. Install skylight at Media -PENDING
  9. Install missing laminate piece at microwave - PENDING
  10. Install missing laminate frame under kitchen cupboard  - COMPLETED


Bin removed

 
Temporary fence and ugly site toilet removed


Weeds at the front removed


Window aluminium corner frame now installed


Metal mesh thing was sticking out before but now fixed


Future driveway
 
Laminate trim to be installed at Microwave area


At last, toilet installed at Ensuite

26 June 2014

Counting down 7 days to handover :))

It is an official counting down 7 days until the day we receive our keys to our new lovely home. It has been such a journey from the day we first met Plantation Homes in February 2013. Mostly are on the good sides, no major problem with Plantation Homes. Happy overall, just can not wait to hold the keys in our hands!

Early this morning we had another quick site visit with Andy as he would like check with us with the kitchen island cabinet and the light point at Master Suite WIR that we mentioned. So the cabinet maker has fixed the island cabinet height by cutting from the bottom (instead of re making a whole new cabinet) and it looks MUCH better having it at very similar height to the rear bench (approx 20mm difference). On the other hand, while we were at the kitchen we saw the glass splash back has been installed but guess what? It's NOT the same colour as the sample we got from Cosham Studio!! We showed Andy the sample piece which has the colour sticker name 'Russian Toffee Sparkle' and our colour selection document actually says 'Russian Toffee Mirror Flake'. So Andy is going to investigate and get back to us. He said if this an error they need to break the whole glass splash back and order new splash back which could take up to 10 days. Oh my my.

Issues aside, Stegbar has installed our shower screens, towel rails, vanity basins, mixers, shelves, door handles and removed the clear frosted sticker thing on the windows. Now you can actually see inside of the house from outside clearly. While we were on site, the fly screen man came to install the fly screens so I guess not much left to be done.

Pretty much we are at 98% completion. Next Monday we will meet with Andy again and the painter to go through the touch up. This is where we need to carefully inspect every corner of the walls and tell the painter where to touch up.

  1. Painting internal walls - COMPLETED
  2. Install island bench, shelves to WIL and WIR - COMPLETED
  3. Install Master Suite door - COMPLETED
  4. Install front entrance door and stain to rich chocolate - COMPLETED
  5. Install kitchen and laundry sink - COMPLETED
  6. Install shower screens, bath tubs and vanities - COMPLETED
  7. Install kitchen and bathroom taps/shower head - COMPLETED
  8. Install fly screens to windows - COMPLETED
  9. Install light switches, powerpoints and lights - COMPLETED
  10. Install ducted air conditioning - COMPLETED
  11. Install garage door and roller door - COMPLETED
  12. Install solar hot water bottle - COMPLETED
  13. Install gas bottle - PENDING
  14. Electrician to move the ceiling light point at WIR to centre - PENDING
  15. Andy to advise about the glass splashback - PENDING
  16. Andy to advise about the dent on the fence - PENDING
  17. Install the last toilet suite - PENDING
  18. Install exhaust fan at PDR - PENDING
  19. Install window corner frame at front - PENDING
  20. Install skylight at Media - PENDING
  21. Install laminate piece at microwave - PENDING
  22. Install laminate frame under kitchen cupboard - PENDING
 


Ensuite

Ensuite
 
Ensuite


Master Suite WIR

 

Shelves now in the bedroom robes

PDR. Obviously the guys has been using our toilet!
 
 

Bathroom
 
Double towel rail at Bathroom
 
Island bench now at similar height to rear bench

Our incorrect colour splash back. It looks more cream in reality

From the backyard

Side of the house

Our solar hot water

17 June 2014

Quick inspection with site supervisor

This morning we met up with our site supervisor, Andy, to inspect around the house as we have a few questions. So Andy advised most of our concerns will be addressed at the final building inspection that's when they go around the house and check every corner if there is something needs to be fixed it will be fixed at the inspection. And about our Master Suite door got delayed until now was because wrong door height was delivered so they had to send it back and apparently these doors were from Melbourne so it took sometimes to get new door in.

Walked around the house did not see a lot was done. Shower and bath mixers got installed at Ensuite and the bathroom only has the bath mixer installed . Still pending for shower screens, vanity basins, shelves and toilet seats to be installed. These will be done by Stegbar and they are booked on 26 June if I heard it right. One of the subcontractor who drilled a hole into the wall tile to install the shower mixer at the bathroom he actually cracked the tile and wrote 'sorry' for the tiler (lol). Well, here come the tiler again :)

So finally our kitchen and ensuite/bathroom caesar stone bench top got installed but guess what!? Our kitchen island cabinet was made at incorrect height!!! Yes, INCORRECT HEIGHT! It was hard to tell when the kitchen cabinet installed until the caesar stone bench top go in then you can immediately see the island bench top is a lot higher than the rear bench top. Approx 30mm difference in height. Apparently, this was the cabinet maker error that they did not refer to the amended drawing that Plantation Home sent and went with the original drawing. So now they have to rip the cabinet apart (keep the island bench top of course) and install new cabinet. On the good side, Andy assured this will not delay our handover date on 3rd July :)

A couple of more photos will be added shortly.


Ensuite shower mixer installed

Caesar stone bench top installed. Pending for vanity basins and mixers

Bath mixer installed. The mixer is a bit long and stick out a bit :(

And finally Master Suite door installed (unpainted)

Garage door installed. The door will be adjusted to touch the ground once electricity is installed.

Roller door installed

Scratched marks on door frame at Garage

Laundry sink and mixer installed

Toilet seats and towel rails to be installed

Semi recessed at Powder room installed. Pending for mixer

Caesar stone island bench and rear bench installed

As you can see the island bench is higher than the rear bench (!!)

Caesar stone rear bench installed

Posh kitchen sink installed (upgraded). Pending for mixer

11 June 2014

We got a HANDOVER date !!!

We thought the call we received today from our administrator was about some minor issues that we raised but she actually have a good news for us - our handover date will be 3rd July! Whooohooo! We are certainly excited that its so much earlier than our initial thoughts. So that is 3 weeks away now we need to get onto some important things such as getting quotes for driveway, landscaping, decking, security screens, curtains/blinds and also need to choose our carpet again as the carpet colour we originally chose was too dark. We need something lighter to balance out the colours of furniture we are purchasing. Andrew will be emailing us about the minor issues we raised, do hope they get something fixed before handover.

Still haven't seen much of movement since painting has completed other than solar hot water bottle, garage door and roller door installed. Bathroom items such as bath tubs, toilet seats, towel rails and shower heads are delivered but not yet installed. Still no sign of caesar stone island bench top, shower screens, master suite door and robe shelves. Pretty much only minor things left needs to be done inside. For outside, we're not sure if they going to flatten the soil around the house but let's hope they will.

07 June 2014

And finally painting has completed!


Though it has been frustratingly slow but gladly to say the external and internal painting has now completed after an almost 2 weeks. We are happy how the colours turns out especially with the render facade as the first coat looked a bit 'pinkish' but now it looks much better. 

Our front door also got installed and stained. The only door left yet to be installed is our Master Suite. Not sure what is the delay to have this installed.

Not much of a progress other than receiving a text from Origin advising our LPG solar hot water bottle is scheduled to be delivered on Tuesday.

Yesterday, we shoot an email to our administration mentioning a few things we noticed while inspecting the house. Nothing major just things such as alfresco door not locking probably (the frame might be made incorrectly), door to garage makes squeaky sound when opening/closing, paint chips on gutter at front, a metal mesh thing stick out at top of render porch, electrician poked a hole at Laundry to install the light switch at WRONG HEIGHT (higher than all other light switches), etc. So hopefully these get fixed before the handover.

Now back to the waiting game for the followings to be installed:
  1. Painting internal walls - COMPLETED
  2. Install island bench, shelves to WIL and WIR - PENDING
  3. Install Master Suite door - PENDING
  4. Install front entrance door and stain to rich chocolate - COMPLETED
  5. Install kitchen and laundry sink - PENDING
  6. Install shower screens, bath tubs and vanities - PENDING
  7. Install kitchen and bathroom taps/shower head - PENDING
  8. Install fly screens to windows - PENDING
  9. Install light switches, powerpoints and lights - PENDING
  10. Install ducted air conditioning - PENDING
  11. Install garage door and roller door - PENDING
  12. Install solar hot water bottle - PENDING
  13. Install gas bottles - PENDING

Photos now includes completed tiling :))


Front door installed (unstained)



Front door now stained

Master Suite

Living


Ensuite with extended mirror (upgrade)

Ensuite (love the sea-shell mosaic!)

Bathroom mosaic (happy with this mosaic as well)

Bathroom

Bathroom

Bathroom



Looking out to the front door


Kitchen sink delivered a few days ago but not yet installed


Metal mesh sticking out


Paint chips on gutter